In an address read for him by Mr Aderemi Oladapo, General Manager of WAPCo in-charge of Operations at a stakeholder forum, Mr Derickson said in April this year, the company supplied gas to the Volta River Authority (VRA) station at Aboadze under an interim sales arrangement.
However, he said, the company since May this year has ceased to receive gas supply due to the destruction of several hundred kilometers of gas supply pipelines in the Niger Delta region.
Mr Derickson said the company’s compressor station in
In addition, he said, the facilities including the regulating and metering stations that would enable gas to be received from offshore in Tema,
He said once they were completed, WAPCo would have the compression capacity to deliver to VRA enough gas to power four 110 megawatt turbines as well as supply customers in
Mr Derickson said under its Community Development Program, the company had provided health, education and sanitation facilities to a number of communities at a total cost of about GH¢830,000.
Source: Modern Ghana